SIEMENS MEGA PROJECT - World’s Largest Combined Cycle Power Plants

مخرجات المشروع
  • Masader delivered environmental management and monitoring services for Siemens' three 4800 MW Combined Cycle Power Plants located in Egypt's New Capital, Beni Suef, and Burullus. The scope of the project (2017–2019) included:
  • Developing and implementing operational waste management and monitoring plans.
  • Supervising the implementation of the Environmental Management System (EMS).
  • Conducting monthly training sessions on EMS roles, responsibilities, and requirements.
  • Delivering additional training for staff on environmental and social management procedures and integrating QHSE (Quality, Health, Safety, and Environment) standards